Description

The Work includes, but is not limited to: • Project management and administration. • Design and engineering of the Contract object: • Transformer new T9 • Alternative 2: 30 MVA (including 24 kV switchgear indoor) • 145 kV instrument transformers in switchyard, and kWh metering system • 170 kV cable system • 145 kV and 24 kV surge arresters in the new transformer bay • 24 kV cable system • 24 kV switch-disconnectors for arc-suppression reactor • 24 kV switchgear indoor (Alt. 2) • Relocation of arc-suppression reactor in the new transformer bay • 400 V low voltage power supply to new transformer bay • Level measurement in new transformer bay • De-blocking button in new transformer bay • Relocation of voltage regulating relay • Earthing system Removal and destruction of existing equipment that are taken out of operation including: • Existing transformer T9 – optional (Option )

Oppdragsgivere

All notice data

id:
2020-329074
eFormId:
2020-329074
procedureId:
2020-329074
heading:
Transformer T9 - Fortun
description:
The Work includes, but is not limited to: • Project management and administration. • Design and engineering of the Contract object: • Transformer new T9 • Alternative 2: 30 MVA (including 24 kV switchgear indoor) • 145 kV instrument transformers in switchyard, and kWh metering system • 170 kV cable system • 145 kV and 24 kV surge arresters in the new transformer bay • 24 kV cable system • 24 kV switch-disconnectors for arc-suppression reactor • 24 kV switchgear indoor (Alt. 2) • Relocation of arc-suppression reactor in the new transformer bay • 400 V low voltage power supply to new transformer bay • Level measurement in new transformer bay • De-blocking button in new transformer bay • Relocation of voltage regulating relay • Earthing system Removal and destruction of existing equipment that are taken out of operation including: • Existing transformer T9 – optional (Option )
buyer:

1 results

  1. id:
    930 187 240
    name:
    Hydro Energi AS
locationId:

No results.

placeOfPerformance:

No results.

issueDate:
2020-09-28T12:00:00+02:00
deadline:
not reported by source
qualificationDeadline:
not reported by source
noticeType:
ANNOUNCEMENT_OF_CONCLUSION_OF_CONTRACT
allTypes:

2 results

  1. ANNOUNCEMENT_OF_CONCLUSION_OF_CONTRACT
  2. RESULT
allCpvCodes:

2 results

  1. 31100000
  2. 31000000
directCpvCodes:

1 results

  1. 31100000
parentCpvCodes:

1 results

  1. 31000000
noticeStatus:
not reported by source
allReceivedTenders:

2 results

  1. type:
    tenders
    total:
    3
  2. type:
    t-esubm
    total:
    3
preferredPublicationDateTed:
not reported by source
plannedDateTed:
not reported by source
competitionDocsUrl:
not reported by source
sentToTed:
yes
regulationUrl:
https://lovdata.no/dokument/SF/forskrift/2016-08-12-975?q=forsyningsforskriften
core:
estimatedValue:
not reported by source
mainActivity:
electricity
awardedNames:
changeNotices:
not reported by source
limitedDataFlag:
no
publicationDate:
2020-09-28
tedId:
not reported by source
procurementTimeline:

1 results

  1. id:
    2020-329074
    allType:

    2 results

    1. ANNOUNCEMENT_OF_CONCLUSION_OF_CONTRACT
    2. RESULT
    publicationDate:
    2020-09-28
    selectedNotice:
    yes
procurementStrategicLabels:

No results.

lotsNumber:
1
doffin_url:
https://doffin.no/notices/2020-329074

Continue exploring

How an AI agent should use this page

Ground rule: Navigate with HTML GET links to keep explanations and relationships. Use the page's JSON alternative only when concrete values must be extracted, compared or computed.

How to use the procurement page

Check the notice ID, status, publication/deadlines and whether the data comes from Doffin or TED. Follow the buyer to the company page and the delivery location to place search.